Completed -
The scheduled maintenance has been completed.
Apr 4, 03:13 CDT
Verifying -
Verification is currently underway for the maintenance items.
Apr 4, 02:55 CDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Apr 4, 02:00 CDT
Scheduled -
The Azure team will be applying Microsoft updates after 2:00 am CT on Saturday morning to the following C93 environments. To complete the installation process, the servers will be restarted and back online by 7:00 am CT on Saturday morning.
• Prod-Bus-1
• Prod-Web-1
• Prod-SQL-1
Please report any conflicts, otherwise we will move forward with the Microsoft updates.
Thank you,
Azure Team
Mar 30, 14:41 CDT